The ambitious Milburngate development, located in the heart of Durham, has faced significant challenges that have delayed its completion. Originally slated to open by the end of 2022, the project, a joint venture between Arlington Real Estate and Richardson, promised to transform the area with 153 built-to-rent apartments, office spaces, and high-profile tenants such as BrewDog, Premier Inn, and Everyman Cinema. No progress has been made since The Chronicle reported on new images of the unfinished site in October, with the fencing still preventing access to the BrewDog complex.  

Palatinate can reveal that Councillors Amanda Hopgood and Richard Bell (Leader and Deputy Leader of the Council), Ted Henderson, Chris Hood, Susan McDonnell, James Rowlandson, Elizabeth Scott, Alan Shield, John Shuttleworth and Mark Wilkes met in a private meeting on 15th May 2024, to discuss the project. There is a further private meeting scheduled for 12th February 2025. This time, a joint report of the Corporate Director of Regeneration, Economy and Growth and the Corporate Director of Resources, suggesting some progress might be about to be made. 

Construction setbacks arose following the collapse of Tolent, the primary contractor for the site, which went into administration in February 2023. The bankruptcy of the construction firm resulted in the loss of 313 jobs and left the project in limbo. In response, the developers initiated a ’technical review’ of the site, which revealed further issues, including the incorrect application of fire-proofing paint. 

There is a further private meeting scheduled for 12th February 2025

A spokesperson for Arlington Richardson explained to The Northern Echo that “constructive dialogue is ongoing between the parties, with various options now under consideration to deliver a mutually beneficial resolution and enable us to finish this important and significant development for Durham.” The review found that the intumescent paint—a fire-resistant coating that expands to delay the impact of fire—was applied with an incorrect thickness to some steel structures. Remediation work is contingent on reaching an agreement with Durham County Council. 

The delays have drawn mixed reactions from the community. Allison Smith, a Durham resident, expressed her frustration, saying, “That end of Durham is an utter dump.” However, some residents, like Stuart Weir, defended the council, noting, “My understanding is this has nothing to do with Durham County Council. The project was a private, commercial endeavour.” 

Durham County Council have emphasised their continued involvement despite not owning the development. The setbacks have also affected local sentiment, as residents returning to the city after some time away have been struck by the stalled progress. One resident noted online, “I am coming home to Durham in two weeks for the first time in a year. I can’t believe this project has not been completed yet.” 