Plans for data centre near Durham City in initial stages

By Amee Joshi

Plans have been unveiled for an eight-building data centre just miles from Durham City.

US based data centre developer Tract plans to build the project, labelled Durham Technology Park, on land between South Hetton, Murton, and Easington Lane- approximately 8 miles east of Durham City.

The proposed data centre’s first designs include seven main data centre buildings, dubbed ‘data halls’, a logistics building, and car parking, as well as internal roads and footpaths.

The site could hold up to 500 megawatts of electrical capacity, and would draw its power from a 400-kilovolt main Grid substation currently being built in nearby Hawthorn Pit.

The project would be Tract’s first entry into Europe, having already built 14 data centres across 6 US states. 

Tract described itself as “a leading global developer of data centre campuses”, bringing together “highly skilled teams and trusted community partners to create construction-ready projects that support the UK’s growing digital demands and deliver lasting local value.

“Our vision extends beyond the data centre itself. Through thoughtful masterplanning, we consider how each project can contribute to its wider setting through new infrastructure, landscape and biodiversity, employment, skills, services, and opportunities for local investment.

The result is a coordinated, sustainable development that supports digital growth while creating a positive and enduring legacy for the communities in which we operate.”

Tract plans to build the project, labelled Durham Technology Park, on land between South Hetton, Murton, and Easington Lane- approximately 8 miles east of Durham City

The developer also assured the project will benefit the wider community through creating employment opportunities. 

It estimates that the site’s building stage could generate up to 1500 construction jobs, and indirectly support 1470 jobs through supply spending. 

After it opens, Tract expects the data centre to employ around 310 staff across different fields, and indirectly provide a further 740 jobs.

The company added it is “committed to working with both Durham County Council and Sunderland City Council to establish clear routes for employing local people through construction labour, technical apprenticeships, specialist subcontractors, and operational support services”.

It also argued against a number of environmental concerns commonly levelled against data centres. 

Regarding water usage, Tract said “in close collaboration with Northumbrian Water, the [water cooling] system will be designed and constructed to ensure adequate capacity, both volume and system pressure, for all customers”. 

It added that “there are no toxic chemicals used in the data centre; therefore, no potential for toxic discharge that would impact water quality.”

Residents living near data centres around the world have voiced concerns over their visual impact and its repercussions for local house prices. But Tract promised “a landscape masterplan will be developed to provide new planting that fits in with existing landscape character, which will help to soften the buildings and ground level activity within the landscape and views over time.”

On biodiversity concerns, the company said it would submit a Preliminary Ecological Appraisal, alongside habitat and species surveys, and commit to a mandatory Biodiversity Net Gain plan, which will require it to “deliver at least a 10% increase in biodiversity value, secured for a minimum of 30 years”.

Noise pollution from data centres has become a growing source of frustration for nearby residents, resulting in several high-profile lawsuits against operators. However, Tract commented that its data centres are “designed with a wide range of noise-reduction measures, such as sound barriers and insulated walls”, and that “a detailed noise impact assessment is being undertaken”, which will “demonstrate how the noise generated by the development will not be at unacceptable levels above the background noise levels of the area, when in surrounding public places and houses”.

The developer cited the site’s proximity to the Hawthorne Pit substation- which is being built under the Eastern Green Link 1 project to import offshore wind energy- as the reason for its location, saying it is “uniquely positioned to meet the specific locational requirements of data centres”. 

Tract expects construction to take 8 years, starting from 2027. It plans to submit an outline planning application to Durham County Council this December- after it has considered residents’ responses- but emphasises the project is still in its initial stages, and that it “does not know at this time” who the site’s operators would be.